Project History

Collaboration on Pukwis began in 2003 and has advanced steadily in accomplishing pre-construction milestones. Pukwis Phase I (20 MW) is now ready to move from feasibility to construction.

Major Milestones:

  • Awarded a Feed-in Tariff contract (20 year power purchase agreement) from the Ontario Power Authority on April 8, 2010
  • Secured GTA site with capacity for 20 MW wind farm
  • Compiled 3 years of wind resource data
  • Initiated Environmental Assessment (long lead time bird and bat studies are completed)
  • Pukwis Energy Co-op incorporated, target date for release of Co-operative share offering is Q2 2011
  • Completed windmill micro-siting and grid connection engineering studies